Wednesday, February 15, 2012

Updates on Renovation 8

Received a call in the morning by the electrician and his call made me curious about how he will tear out the cables as I could not visualise the scenario after his description. The trip down made me understand what he meant by not touching the bigger wire casings. If you are able to see from the photos, what he meant was that there was a big horizontal wire casing at the ceiling of each room and he did not took those down otherwise all the wires will be in a big mess.

The wires removed from its housing 1

The wires removed from its housing 2

The socket removed from its resting place

The wiring of the kitchen was also put up as well.

The wiring in the kitchen

We also took the photos of the lights that previously had their glorious days on the ceiling and I did not realise that the lights can actually caused burnt marks on the ceilings.

The fall of the old lights 1

The fall of the old lights 2

The fall of the old lights 3

The shadows of the old lights

The water pipes were sort of done as well, together with the flooring of the service balcony.

The water pipes 1

The water pipes 2

The water pipes 3

The completed service balcony

After that check, we went for our V-day dinner. A lot of places seemed to be packed and thus we opted for Hanis at the basement of East Point in order to save time, as we need the time to do work.

The V-day dinner

Hers

His

On the following day, the doors and windows are up. Even though it did not follow the orientation of our last updated instructions, but I guess it turned out quite well. Sometimes the absent-mindedness of our contractor can bring in some nice and pleasant surprises.

MBR toilet door (open)

MBR toilet door (closed)

Common toilet door (open)

Common toilet door (closed)

MBR toilet windows

Common toilet window (outside)

Common toilet window (inside)

The inner window at the kitchen

Shall bring more updates soon.

Monday, February 13, 2012

Updates on Renovation 7

Hmm, more progress on the tiling of the balcony and service balcony, but the workmanship seemed to be poorer than the previous two weeks. The tiles for the service balcony were like cut to weird sizes, not sure if it can be seen from the photo. The water piping seemed weird also as it seemed to run through quite a number of places.

Flooring of balcony

Flooring of service balcony

Water piping at bottom of MBR toilet

Water piping at top left of MBR toilet

Water piping at bottom left of MBR toilet

Water piping at bottom of common toilet

Water piping at top of common toilet

Water piping at kitchen

The dented piping which I think need to be changed

Sunday, February 12, 2012

Viewing of Edited Wedding Photos

It was quite exciting to be viewing our edited wedding photos, which will be printed into the albums. The effects for most of the pages turned out well. For those that did not, we made our comments and hopefully the photos will be alright after the changes are made. They will be sending us the new ones via email and once we approved of them, it will be printed. No photos for now but we managed to get our raws.

We also bought a bicycle, though it had been quite a while since I last cycled. The control of the bike was rather weird as the bike tended to swerve very easily to the left or right. Probably it needed some tightening of the nuts. And we cycled from our new place to my place. I guess my dear loved the romantic ride a lot =)

Updates on Renovation 6

I had been going down to take a look everyday and the progress so far had been good. Though there were some issues regarding the adherence to the originally discussed plan (like the placement of the kitchen sliding door and its corresponding track), that was soon sorted out and I guess things should be more or less done next week. We had also decided to go ahead with plastering and relocation of the electrical sockets, despite the extra cost and we took out some items as well. The workers were quite nice too, though I thought that their progress can be further improved. You can actually do photohunt for some of the photos.

Day 10: MBR toilet with the shower section done

Day 11: MBR toilet with floor tiles done

Day 9: Common toilet w/o floor grout

Day 10: Common toilet with floor grout

Day 9: Service Balcony

Day 12: Washing machine base

Day 9: Back of the kitchen wall

Day 11: Kitchen with its floor tiles

Day 12: Plastering of the kitchen (front)

Day 12: Plastering of the kitchen (back)

Day 12: Plastering of the kitchen (side)

Day 12: Fridge base

We also received the items that we bought previously. As such, we were also getting a big hole in our pocket. Interestingly, it was only the third time in my entire life that I actually spent an amount that consisted of four digits before the decimal point. Similar to the renovation, so far so good and took a lot of pictures of them. While waiting for the delivery of the items, we continued on our mini project of removing the solar film from the window panes. Not a very good idea as the glue of the film was stubbornly stuck to the glass. On hindsight, perhaps the $300 to get others to do it is really worth it.

Dear's creative creation

Our sink and accessories arrived 1st

The basin came thereafter

So did the water closet...

... and the mirror cabinets and towel racks

The late arrival of the oven

The pretty glass hob

The instant water heaters

The unopened hood

Just to update, we also bought our bedside table and in the process of confirming the bedroom wardrobe.

My dear also made one comment which I felt was interesting: The best time to buy a house is now! The reason is shown in the picture below. I guess we were relieved and glad that we settled for our house that time, otherwise we will be having a headache in terms of the money which we need to fork out. Guess that the high COV that we paid can be considered to be relatively alright now and we do not feel so heart pain. Sigh, the housing situation now seemed to be so dire.

The never-ending climb